December/2012 Thought it would be good to build a house
lots of time spend looking at land options and house options

28/01/2013  Appointed Coral to draw up plans
11/02/2013  Land Survey
06/03/2013  Formal finance approval for land purchase
20/03/2013  Receipt of fixed price Contracts
23/03/2013  Signed contracts with Coral, submitted variation for allowance items
02/04/2013  Land purchase
03/04/2013  Lodged application for covenant approval
06/04/2013  Lodged formal application for setback relaxation requested that Coral update plans to move property forward on lot
16/04/2013  Paid 5% deposit
19/04/2013  Formal construction approval received
23/04/2013  Received amended plans
24/04/2013  Covenant approval
26/04/2013  Appointment of Private Certifier
04/05/2013  Tile Selection
10/05/2013  Clipsal Selection
17/05/2013  My Choice
28/05/2013  Council Approval
02/06/2013  All planning and approvals complete and given start date
20/06/2103  Site scraped and temp drive and drainage installed
21/06/2013  Start date
24/06/2013  Piers poured
26/06/2013  Plumbing Installed
03/07/2013  Slab Poured
12/09/2013  Frame Completion
22/07/2013  Roof completed
23/07/2013  Electrical cabling Installed
24/07/2013  Plumbing pipework installed
25/07/2013  Solar system botch install!!!
01/08/2013  Dry lining complete
02/08/2013  Brickwork Complete